Swimming pools | North York, ON

High-Torque Foundation for Hillside Pool Addition

We installed the foundation for an indoor swimming pool home addition in North York. The site had a steep slope, a tight backyard and fractured rock at 2 meters, so the piles went in at varying torque under an on-site geotechnical engineer.

Request a Quote (289) 221-5711
twenty foot deep helical piles

Structure

Residential indoor pool addition

Location

North York, ON

Piles

54 helical piles

Pile size

4 1/2″ x 10′ with 10′ extensions

Installed depth

16 to 20 feet (5 m minimum embedment)

Installation torque

12,000 to 25,000 ft-lbs

Crew

2 certified installers plus support labour

Engineering

On-site geotechnical engineer

Project overview

The homeowners were adding an indoor pool to their house. A filled concrete pool is among the heaviest loads a home foundation carries, so the piles had to reach stable ground well below the surface. We installed 54 piles to a minimum embedment of 5 meters.

installing fifty four helical piles
twenty foot deep helical piles

The challenge

The backyard could only be reached through restricted access, so materials and equipment came in carefully through excavated trenches. The site also sat on a large hillside slope, and at 2 meters down the crew hit a dense layer of fractured rock that needed specialized equipment and experience to push through.

The DiamondTech solution

Two certified installers drove the piles to final depths between 16 and 20 feet. Torque was varied from 12,000 to 25,000 ft-lbs depending on the pile location and soil resistance. An on-site geotechnical engineer was there for the whole job and recorded the torque and depth data for every pile.

Why helical piles suit a pool addition

  • No excavation spoil or soil displacement, which matters on a slope.
  • Compact equipment fits tight backyards where a drill rig would not.
  • Torque readings confirm each pile’s capacity as it goes in.

Project summary

For this hillside pool addition in North York, DiamondTech Piles installed 54 helical piles with a 4 1/2″ shaft, each driven to between 16 and 20 feet at 12,000 to 25,000 ft-lbs of torque. A two-installer crew worked in restricted backyard access and through fractured rock, with a geotechnical engineer documenting the in-field data.

Project photos

Pool foundations in North York and beyond

This job is one of many residential helical pile installs in the GTA. Our page on helical pile foundations in North York covers local site conditions, and our guide explains how helical piles work.