144 M4 helical piles installed to 28,000 ft-lbs of torque under the steel frame of a commercial building in Scarborough, completed in three weeks.

Commercial project | Scarborough, ON

144 Helical Piles for a Commercial Building in Scarborough

Our crew installed 144 M4 helical piles under the steel frame of a commercial building in Scarborough, each one turned in to 28,000 ft-lbs of torque.

Request a Quote (289) 221-5711
Helical pile shafts standing in rows across the slab area under the steel frame of a commercial building in Scarborough

Structure

Commercial steel-frame building

Location

Scarborough, ON

Piles

144 M4 helical piles

Shaft

4 1/2″

Wall thickness

0.325″

Installation torque

28,000 ft-lbs

Crew and equipment

2 installers, 8-ton excavator

Time on site

3 weeks

144 piles under one roof

The building’s steel columns and roof framing were already standing when we arrived, so every pile went in underneath the structure. The finished piles run in long rows across the floor area of the building.

Excavator turning a helical pile into the ground beside a scissor lift and stacked pile shafts in Scarborough
Helical piles with welded helix plates laid out on the gravel ready for installation

Heavy-wall M4 piles

The M4 is our 4 1/2″ shaft, listed with the other large-diameter sizes on our helical pile specifications page. For this job the shafts had a 0.325″ wall, and each pile was installed to 28,000 ft-lbs of torque.

Two people and an 8-ton excavator

The whole install took two people: a machine operator running the 8-ton excavator and a ground control member working beside each pile as it went down. An 8-ton machine is compact enough to work between the building’s columns, and the pair finished all 144 piles in three weeks.

Excavator with its drive head raised over a pile position while ground crew check the layout

Project summary

For this commercial building in Scarborough, DiamondTech Piles installed 144 M4 helical piles with a 4 1/2″ shaft and a 0.325″ wall, each turned in to 28,000 ft-lbs of torque. A two-person crew working from an 8-ton excavator completed the installation in three weeks, inside a steel frame that was already standing.

Project photos

Commercial foundations in Scarborough and beyond

This job is one of many in our commercial and industrial helical pile work. If you’re building east of the city, our page on helical pile foundations in Scarborough covers local permits and site conditions. New to screw piles? Our guide explains how helical piles work, from the helix plates to torque readings.